Skip to main content
Smart Cities Marketplace
Scalable cities

Excess heat recovery from sewage water in Cologne, Germany

mini_126-Photo-by-Kai-Dahms-Unsplash

Details

Publication Date
Solution
Celsius Toolkit

Solution type

Celsius toolkit

The main objective of Cologne’s Demonstrator is to recover excess heat from sewage water and use it in decentralized local heating networks by supplying heat and DHW to local school buildings.

 Figure 1. Three demonstrator sites in Cologne. 

Asset

Idea and layout

 Figure 2. The main components of the demonstrator system.

The CO1 demonstrator consists of three different operation sites; Wahn, Mülheim and Nippes. In all sites, sewage source heat pumps recover heat from sewage water. The main components of the system are heat exchangers, water-to-water heat pumps, gas boilers and heat buffer tanks. One innovative part of the demonstrator is the heat exchanger, which is installed inside the sewage pipe. This indirect heat extraction technique is used in two of the demonstrator sites (Wahn and Mülheim). In the third site, a direct heat extraction technique is used. This means part of the sewage water is passed and pumped direct to the evaporator of the heat pumps.

Facts about the case
Annual thermal energy provided:
1109 MWh (Wahn) and 762 MWh (Mülheim)
Heat source:
Excess heat from sewage water (at least 12°C)
Energy efficiency:
116% in Wahn and 128% in Mülheim
Annual greenhouse gas savings:
214 tonCO2e in Wahn and 150 tonCO2e in Mülheim
Period:
2012-2016
Support:
FP7-supported Celsius Project

Impact

The overall demonstrator’s performance is summarized in the following table according to 5 evaluation criterions. It can be noticed that the assignment of all the scores is directly linked to the values calculated for the Key Performance Indicators, except for socio-economic benefits where a qualitative assessment is carried out based on this cluster’s indicators and on separate interviews.

Overall Impact Fair/Medium
Size [MWh/y] 1-100 100-1000 1000-5000 5000-10000 >10000  
Primary Energy Savings 0-10% 10-20% 20-40% 40-60% >60%  
GHG Emissions Reduction 0-10% 10-30% 30-60% 60-90% >90%  
Pollutant Emissions Reduction 0-10% 10-30% 30-60% 60-90% >90%  
Socio-Economic Benefits Low Fair Medium High Extrem  

Replicability

Replication potential

The assessment of potential for replication of demo technologies is based on the results of the whole monitoring phase. General replication requirements for demo technologies are assessed through seven criterions including availability of the exploited source, adaptation to different climate conditions, ease of authorization, implementation and operation, required investment cost.

Overall replication potential Medium-High
Criterion 1 2 3 4 5  
Availability of required conditions Need for conditions currently not available in Europe Conditions available in a small part of Europe(< 20%)

Fair availability of required conditions

(20-60% of Europe)

Conditions available in a large part of Europe

(60-90%)

Conditions available in all areas (> 90% of Europe)  
Adaptability to different climates Solution not compatible with European climate conditions

Solution applicable only in a small part of European climate areas

(< 20%)

Solution fairly applicable to European climate areas

(20-60% of Europe)

Solution applicable to climates of a large part of Europe

(60-90%)

Solution compatible with all climate areas in Europe (>90%)  
Ease of authorization Lack of a normative framework

Long time needed for authorization

(> 6 months)

Medium time required for authorization

(3-6 months)

Short time needed for authorization

(< 3 months)

No need for specific authorization  
Ease of operation Strong maintenance need and effort to guarantee operation Significant time and effort needed for functioning Maintenance and operation effort in line with other suitable alternatives Low effort required for technology operation Almost no need for maintenance and very limited effort for operation  
Integration of waste energy sources Technology not allowing any recovery of waste energy sources Solution allowing a limited waste energy recovery (<20%) Technology relying on a fair share of waste energy (20-50%) Solution exploiting a significant amount of waste energy (50-80%) Technology relying almost only on waste energy sources (>80%)  
Low CAPEX requirements CAPEX needs much higher than conventional alternatives (> +80%) Capital investment slightly higher than conventional solutions (+20-80%) Capital investment in line with conventional alternatives (±20%) Solution cheaper than conventional alternatives (–20-80%) CAPEX requirements almost negligible compared to conventional alternatives (<–80%)  

Considering the replication potential at European level, more than 84% of EU population is connected to a sewage network, share which increases if focusing the analysis on urban areas only; this means that the replication potential for the Cologne demonstrator is particularly high, also due to the adaptability to different climate conditions and the use of conventional technologies that are economically viable. According to the analyses carried out within other research projects (e.g.: Stratego), 5% of total heat demand could be covered with heat recovered from sewage systems in cities and towns.

Technical requirements

The technology demonstrated in Cologne could be replicated in several places, within the city of Cologne and in other cities over the EU, provided that some minimal requisites are verified. To ensure the economic feasibility of heat recovery from sewage the following aspects are important:

  • Low supply temperature (a 40 °C temperature leads to a COP of 5 whereas a temperature of 70 °C gives a COP of 3)
  • High temperature of sewage (min. 12 °C)
  • High heat demand to pay off the higher investment (min. 150 kW)
  • New construction or refurbishment of the building to be heated
  • Short distance between building and sewage pipe (max. 200 meters)
  • Adequate sewage pipe (minimum diameter 800 cm; dry weather flow 15 l/s)

More information: Guidelines for the replicability of the Cologne Wahn Demonstrator

Stakeholders

Stakeholders Organization Name Organization Type Organization Domain Benefits from demo  
Multi-utility Rheinenergie AG Local energy supply company owned at 80% by the City of Cologne https://www.rheinenergie.com , http://www.smartcity-cologne.de/index.php/celsius.html Practical experience in planning and building implementing heat recovery from sewage network. Investment, cost for use of energy and maintenance are recovered by the price of the heat.  
Municipal waste water company Cologne Steb Municipal sewage company http://www.steb-koeln.de/ Waste water grid screen to locate possible heat recovery sites.  
Technology supplier UHRIG Straßen- und Tiefbau GmbH Producer and Installer of the heat exchanger http://www.uhrig-bau.de    
Research Institute TH-Koeln Educational https://www.th-koeln.de Technical knowledge about recovering heat from sewage network throughout compression heat pumps  
Municipality City of Cologne/Coordination of Climate Protection Public authority www.smartcitycologne.de Increased efficiency and sustainability of public buildings  
End-users School head teachers and caretakers Tenants -- Increased efficiency of heating supply  

Finance

The financial model used in the project is Energy Supply Contracting. RheinEnergie AG planned and operates the heat recovery plant in the buildings. External companies, such as Vießmann (heat pump manufacturer) and URIGH (heat exchanger manufacturer) installed the equipment. The return of the investment and the maintenance costs are recovered by the sale of heat.

Challenges and risks

  • Difficulties in getting permissions for using sewage network for different purposes rather than disposal
  • High investment compared to standard solutions (gas-boiler); heat price required for recovering the investment has to be higher than the heat price of standard-solutions (gas-boiler). Therefore, key factors are:
    • Optimal technical dimensioning to cut the investment to the inevitable.
    • Convincing the customer that the price for the sustainable solution is higher than the standard.
  • Optimal location (sewage pipe nearby, good fill level, high flow rate, high heat demand, low temperature demand etc.) should be assessed. Thus, developing a cadaster map of the sewage network and the heat demand could be a strategic factor.

Lessons learned

Demonstrator development

Following awareness was gained within the project:

  • The operation of the system was not optimal, because the boiler operation was prioritized instead of the heat pump operation. A new management control system was installed and optimized the system operation. The gas boiler now supports the thermal energy production in times of higher demand
  • Due to customers request the boiler capacity was 1MW sized and thus oversized. The heat generators should be sized according a heat simulation test so that the optimal heat production can be achieved.
  • In order to modify the sewage pipe system a bypass solution was implemented in the Cologne Nippes site. To recover the thermal energy a bypass from the sewage network to the heating room had to be built. Being the purpose of this bypass, out of the intended purpose of sewage permissions. Some extra permission(s) had to be complied causing a delay in the demonstration realization process. In the past, the law in Germany did not foresee other purpose to operate sewage pipes than disposal. The city authority checked the risks of environmental pollution due to e.g. leakages etc. Furthermore, it was checked if anybody else could be affected by the bypass construction. Therefore,
  • It has to be taken into consideration, especially when it’s the first time, some extra time for the permitting phase to allow appropriate authority approving the modification(s) in the sewage system.
Cologne Wahn

All project phases were successfully completed and the system is in operation since October 2013. However, the measurement devices did not start operating until March 2014. For this reason, the data collection of this demonstrator site started in the before mentioned month.

The following challenges occurred during the operation phase:

  • After the first monitoring period, a lack of data was detected. The malfunction of the measurement devices (sensors, communication equipment) caused this problem.
  • The control system of the demonstrator was not working in an optimal way. It was prioritizing the operation of the gas Boiler instead of the heat pump operation. This means that the gas boiler was supplying most of the heat demand of the school and the heat pump was rarely operating. A new control system was designed for this demonstrator. The new control system was successfully installed, and it is in operation since July 2015.
Cologne Mülheim

All project phases had been successfully completed and the demonstrator site Mulheim started operation in November 2014.

  • Some of the measurement devices have not been working properly, causing some missing data.
  • From November 2015 to Feb 2016 the HP was out of operation due to a problem with the heat exchanger inside the sewage. Due to an overflowed in the sewer channel, the heat exchanger was damaged. The repairmen work lasted almost forth months as special permits have to be managed and no previous experience existed in this field.
Cologne Nippes

After some delay of the heat pump delivery, the operation site Nippes accomplished all project phases and started operation in February 2015. However, in May 2015 due to malfunctioning of some systems components the operation stopped. The demonstrator site in Nippes is not using any heat exchange, but rather the sewage water is been bypassed to a retention basin where a well pump sends the water to the evaporator. This variation in the layout has not been successful. The operation of the heat pumps has been very unstable. The following unexpected issues have raised:

  • One of the two pumps had to be inspected due to high operation noise.
  • The actual water flow rate is lower than expected.
  • The pump gets easily clogged even if it is provided with a lattice and chopper.
  • The heat pump manufacturer went bankrupt after many weeks of uncertainty and rescue attempts.

Several measures at the sewage pump seem to solve the problems so far, but there are few operating hours to prove that they work stably. Test and optimization of the evaporator will start in the next heating period (10/2017).

Demonstrator monitoring

Following the monitoring methodology set up to analyze the Celsius demonstrators, relevant key performance indicators are identified for this technology. The methodology aims to quantify the impact of the new demonstrators with respect to the specific baseline situation. The base line situation refers to the previous heating technology, in this case, gas boilers. The following table shows the calculated parameters for the baseline situation of the year 2014 for both demonstrator’s sites. This calculation changes every year, since each year the heat demand varies.

Baseline parameter Wahn (2014) Mulheim (2014)
Boiler power [kW] 1370 940
Gas consumption [m³] 1500 1000
Annual percentage of use [%] 85 85
Primary energy consumed [MWh/year] 1650 1100
CO2-Emissons [t/year] 272 181
SO2 [kg] 21 14
NOx [Kg] 306 204
Particulate matter [kg] 12 8
Heat supply [MWh/year] 1220 850
Primary energy efficiency 1,35 1,29

Once the parameters for the baseline are calculated, they are compared with the measured parameters of the new technology in order to obtain the KPI's. The following table shows the calculated KPI's, since the demonstrator sites in Cologne went online.

KPI's Unit Wahn (2014) Wahn (2015) Mülheim (2015) Wahn (2016) Mülheim (2016)
Energetic KPI's            
Yearly amount of thermal energy provided by the new system MWh/year 704 1109 719 1015 762
Saved PE in comparison with baseline MWh/year 118 289 216 411 166
Energy efficiency of the project % 110 116 136 148 128
Energy recovery from waste/renewable sources MWh/year 95 286 237 371 252
Environmental KPI's            
Yearly GHG savings in comparison with the baseline % 5 14 16 22 8
Yearly GHG emissions related to the project ton CO2e/year 149 214 130 177 150
Yearly pollutant emissions related to the project %
SO2: 8
NOx: 111
PM: 4
SO2: 12
NOx: 169
PM: 7
SO2: 6
NOx: 87
PM: 3
SO2: 7
NOx: 108
PM: 4
SO2: 7
NOx: 96
PM: 4
Yearly reduction of polluting emission in comparison to baseline %
SO2: 5
NOx: 65
PM: 3
SO2: 8
NOx: 109
PM: 4
SO2: 6
NOx: 85.5
PM: 3
SO2: 10
NOx: 147
PM: 6
SO2: 6
NOx: 87
PM: 4
Carbon footprint ton CO2 /year 149 214 130 177 150
Ecological footprint ha          
Economic KPI's            
Yearly depreciation rate per saved PE €/kWh .35 .14 .16 .1 .21
Yearly depreciation rate per ton of saved CO2e €/t CO2e 5030 1238 1438 833 2672
Total cost (yearly depreciation rate + OPEX) per kWh of saved PE €/kWh .47 .19 .21 .14 .28
Total cost (yearly depreciation + OPEX) per ton of saved CO2e €/t CO2e 6803 1675 1918 1127 3565
Social KPI's            
Number of users benefiting of the new project - 1310 735 1310 735
End user complaints due to the implementation of new system - 0 0 0 0
Surface area served by the new system m2 20650 11199 20650 11199

The following chart shows the KPI "primary energy savings" of the demonstrator sites in Cologne. This KPI is usually higher in the demo site Wahn, as the heat demand is always higher. The variation over the years of this KPI, depends on the operation hours of the heat pump and the outside temperatures, which varies the heat demand. Maintenance and other factors affect the value of this KPI too.

Cologne, GermanyReUseHeat2012 - 2016IVL Swedish Environmental Research InstituteRheinenergie AG, Steb, UHRIG Straßen- und Tiefbau GmbH, TH-Koeln, City of Cologne/Coordination of Climate ProtectionRhein Energie, Fachhochschule Köln, D'AppoloniaCelsius Initiative

Related Celsius content:

Don’t waste the waste water: Clean energy from sewage

Energy recovered from sewage water in Sandvika, Norway

Excess heat from sewage in Hamburg and Singen, Germany

References:

  1. Heat recovery from sewage. Feasibility study 2012 (Rheinenergie)
  2. D4.3 progress and achivements on demonstrators SC London Nov 2015 (Celsius project)
  3. D4.3 progress and achivements on demonstrators SC Genoa May 2016 (Celsius project)
  4. D4.3 progress and achivements on demonstrators 2017 (Celsius project)

External links:

  1. The Cologne demonstrator
  2. Rheinenergie
  3. Fachhochschule Köln
  4. D'Appolonia
Replicability
Low
Medium
High
Authorizative easiness   x  
Adaptability to different climate conditions     x
Technology easy-to-implement (No need of specific technical requirements)     x
Easy-to-implement (No need of specific technical requirements)     x
Easy-to-operate (No need of specific technical requirements)     x
Opportunity of integrating waste energy sources     x
CAPEX needed for the deployment of the solution   x